If you've walked past the empty John Sevier Center downtown, today matters. Johnson City commissioners will consider a range of voting items Thursday, including incentives for the John Sevier hotel project and a data center moratorium.
On Friday, Nov. 13, the Johnson City Development Authority approved an incentive proposal that includes transferring the John Sevier Center to Lansing Melbourne Group for a planned $65 million renovation. The historic building would become a hotel with shopping, dining and entertainment.
The downtown deals by the numbers
- $65 million
- planned John Sevier renovation
- $4.026 million
- to buy the Downtown Centre
- $854,000
- estimated yearly sales and hotel tax revenue
Source: Elizabethton Star
- Upkeep: JCDA spends more than $60,000 monthly on the vacant John Sevier
- Downtown Centre: 37,000 square feet of ground-floor commercial space
- Tenants: ETSU classrooms and a Johnson City police substation
That same day, the Industrial Development Board approved the purchase of the Downtown Centre from the JCDA, with money from the city's Economic Development Reserve Fund. Chairman Gerald Thomas said rebuilding a parking structure that size would cost an estimated $10 million. About 150 of the building's 343 parking spaces will be leased for future hotel use.
About 150 of the Downtown Centre's 343 parking spaces will go to hotel use
150parking spaces to be leased for future hotel use
Source: Elizabethton Star
View as table
| Value | |
|---|---|
| parking spaces to be leased for future hotel use | 150 |
Sources: Johnson City Press, Elizabethton Star